Tool And Die Design Safety Recommendations

These guidelines help you to consider health and safety when designing plant, structures or substances.

Download:

PDF

Health and Safety by Design: an introduction (PDF 3.2 MB)

Key points

  • Designers have an important role in managing health and safety risks.
  • There are key principles of Health and Safety by Design that designers should follow.
  • There are specific things to consider when designing structures, plant or substances.

1.0 Introduction

1.1 Who is this guidance for?

These good practice guidelines are for persons conducting a business or undertaking (PCBUs) with a role in designing structures, plant or substances. These people may include:

  • designers
  • PCBUs who are employing or engaging designers of structures, plant or substances to be used, or could reasonably be expected to be used, at work
  • people who make decisions about the design or redesign of structures, plant or substances
  • external experts who contribute to design projects.

The guidelines are for people who want to learn about designing with health and safety in mind.

1.2 What does it cover?

Designers are 'upstream PCBUs'. An upstream PCBU's duties are important because they can influence the health and safety of products and structures before they're used at work. The guidelines explain these designer duties, and describe how designers can manage health and safety risks (called 'Health and Safety by Design'). These guidelines could be used for projects of varying sizes.

The guidelines:

  • begin with general concepts that cover the Health and Safety at Work Act 2015 (HSWA)(external link)
  • look at the key principles of Health and Safety by Design
  • describe Health and Safety by Design – what's good practice when considering the design of structures, plant and substances.

These guidelines are based on guidance produced by Safe Work Australia.1

Key elements of good practice have been adapted for a New Zealand audience.

These guidelines cover the basic principles of Health and Safety by Design. The Health and Safety by Design process can apply to plant, substances, structures, materials, technology, facilities, equipment, hardware, software  and the way workers interact with these. These guidelines don't cover every aspect listed above, but act as a starting point for PCBUs.

Key points

  • HSWA does not define a 'designer', but for the purposes of these guidelines, 'designer' means any person who prepares or modifies a design, or arranges for or instructs a person under their control to do so. Examples of designers could include, but are not limited to, architects, industrial designers, engineers and software designers.2
  • HSWA (Section 16) defines the term 'design' in relation to plant, a substance, or structure as:
    1. the design of part of the plant, substance, or structure;  and
    2. the redesign or modification of a design.
  • For the purposes of these guidelines, the term 'design' includes drawings, design details, specifications and bills of quantities (including specification of articles or substances) relating to a structure, and calculations prepared for the purpose of a design.2

1  Safe Work Australia Handbook Principles of Good Work Design (2015), Safe Work Australia Code of Practice Safe Design of Structures (2012) ,Safe Work Australia Guide for Safe Design of Plant (2014).

2 Adapted from the UK HSE Construction (Design and Management) Regulations 2015.

2.0 What is Health and Safety by Design?

2.1 Health and Safety by Design

'Health and Safety by Design' is the process of managing health and safety risks throughout the lifecycle of structures, plant, substance or other products. Designers are in a strong position to make work healthy and safe from the start of the design process. Health and Safety by Design is not a separate concept from good design – they are the same thing.

Figure 1 shows the decrease in ability to influence safety that a PCBU has over the lifecycle of a product.

[image] Symberszki chart of influence over a product's lifecycle

Figure 1: Symberszki chart of influence over a product's lifecycle (adapted from Symberszki, R, (1997), Construction Project Safety Planning. TAPPI Journal, 80 (11), 69–74)

2.2 Why is Health and Safety by Design important?

It is important to think about health and safety risks at the design stage. Here's why:

Research illustrates its benefits

International research3 shows the following:

  • Good design can result in significant reductions in work-related ill-health and injuries.
  • Good design reduces damage to property and the environment, and the related costs.
  • Good design enhances the health, wellbeing and productivity of  workers.
  • The most effective risk control measure – eliminating hazards – is often cheaper and more practicable to achieve at the design or planning stage than managing risks later in the lifecycle.
  • The design of plant or structures contributes to a significant proportion of work-related injuries, and solutions already exist for many of those design problems.
  • It is more efficient and effective to manage risk in the design phase than to retrofit health and safety solutions.
  • Design based on Health and Safety by Design principles can reduce the need for retrofitting, personal protective equipment, health monitoring, exposure monitoring, and maintenance.

Smart design of products can help provide a high level of protection for end users

Workers have the right to the highest level of protection, so far as is reasonably practicable. Managing risks in the design stage of a product is an effective way of providing the best protection. It is more effective than, for example, retrofitting a product later in its lifecycle.

Smart design of products makes good business sense

Eliminating health and safety risks before they happen makes good business sense for PCBUs. People who work in safe, healthy conditions are less likely to take time off work and will be more engaged and positive in their job.

This may mean that productivity is increased in the long run.

Health and Safety by Design is also important for developing and maintaining a good reputation to win future work. It gives businesses the opportunity to become leaders in their industry and become the most desirable places to work.


3 Safe Work Australia Work-related fatalities associated with unsafe design of machinery, plant and powered tools 2006-2011 (2014) Safe Work Australia Handbook Principles of Good Work Design (2015)

Safe Work Australia Code of Practice Safe Design of Structures (2012) Safe Work Australia Guide for Safe Design of Plant (2014)

Approved American National Standard ANSI/ASSE Z590.3 Prevention through design – Guidelines for addressing occupational hazards and risks in design and redesign processes (2011)

Health and Safety Executive Research Report RR218 Peer Review of analysis of specialist group reports on causes of construction accidents (2004).

3.0 Health and safety duties

What is HSWA?

The Health and Safety at Work Act 2015 (HSWA) is New Zealand's work health and safety law. It sets out the principles, duties and rights in relation to work health and safety. There are different groups of people that hold health and safety duties under HSWA, called 'duty holders'. They are:

  • persons conducting a business or undertaking (PCBUs)
  • officers
  • workers
  • other persons at workplaces.

A person may have more than one duty (eg a person can be a PCBU and a worker).

More than one person may have the same duty (eg different PCBUs may have the same duty towards the same worker).

For more information on duty holders and their duties, see the Glossary or WorkSafe's special guide Introduction to the Health and Safety at Work Act 2015.

Duties of all PCBUs

A PCBU must ensure, so far as is reasonably practicable, the health and safety of workers, and that other people are not put at risk by work carried out as part of the conduct of the PCBU. This is called the 'primary duty of care'. Figure 2 below illustrates the people who may be affected by a PCBU's work.

[image] chart showing  people who may be affected by a PCBU's work.

Figure 2: people who may be affected by a PCBU's work.

Engage workers about decisions on Health and Safety by Design

PCBUs must involve their workers and their representatives in work health and safety.

PCBUs have a general duty to engage with workers. In addition, they must engage under specified circumstances which include when identifying hazards and assessing risks to health and safety, and when making decisions about ways to manage health and safety risks.

They must also have practices that give their workers reasonable opportunities to participate effectively in improving work health and safety on an ongoing basis (these are known as worker participation practices). This includes processes for workers to report health and safety issues such as concerns that risks are not being adequately managed.

Having worker representatives is one way for workers to participate. Well-established ways to do this include having Health and Safety

Representatives (HSRs), Health and Safety Committees (HSCs) and unions. Other representatives can include community or church leaders.

For further guidance on worker engagement, participation and representation see:

  • WorkSafe's good practice guidelines Worker Engagement, Participation and Representation.
  • WorkSafe's interpretive guidelines Worker Representation through Health and Safety Representatives and Health and Safety Committees.

More than one PCBU can have a duty around the same matter. This might happen in a contracting chain, or when different PCBUs work on the same site. This is known as having 'overlapping duties'.

PCBUs must carry out their overlapping duties to the extent they have the ability to influence and control the matter. They must also, so far as is reasonably practicable, consult, cooperate, and coordinate activities with each other.

Although PCBUs can't contract out of their health and safety duties, contractual agreements can be one way of setting out health and safety expectations for each PCBU. Responsibility to consult, cooperate and coordinate with the designer also applies to contractors and sub-contractors who win a tender.

For more information, see WorkSafe's quick guide Overlapping Duties.

Eliminating and minimising risk

Risks to health and safety arise from people being exposed to hazards (anything that can cause harm). Managing risks involves identifying hazards and then assessing risk to determine which work risks to deal with first, and how the risks should be dealt with.

PCBUs must eliminate health and safety risks arising from work so far as is reasonably practicable. If it's not practicable to eliminate, they must minimise risks, so far as is reasonably practicable. This applies for matters that are within their ability to influence or control.

More information on how designers can carry out risk assessments and manage risks can be found in Section 4 of these guidelines.

For more information about 'reasonably practicable', see WorkSafe's fact sheet Reasonably Practicable.

3.3 Additional duties for designer PCBUs

There are further duties for PCBUs who are designers, manufacturers, suppliers, importers and installers (so called upstream  PCBUs).  Upstream  duties apply to any PCBU that:

  • designs, manufactures, imports, or supplies structures, substances or plant to be used in a workplace; or
  • installs, builds or commissions plant or structures to be used, that could be or reasonably expected to be used, as or at a workplace.

An upstream PCBU's duties are important because upstream duty-holders can influence the safety of products and structures before they're used in work. This may help to eliminate risks. Table 1 below provides an overview of these duties for designer PCBUs.

Duties for designer PCBUs

Duty to, so far as is reasonably practicable, make sure that structures, plant and substances are without health and safety risk

Make sure, so far as is reasonably practicable, the plant, substance or structure designed is without health and safety risks to people who:

  • use the plant, substance or structure at a workplace for its designed purpose
  • handle the substance at a workplace
  • store the plant or substance at a workplace
  • construct the structure at a  workplace
  • carry out reasonably foreseeable workplace activities (such as inspection, cleaning, maintenance or repair) in relation to:
    • the manufacture, assembly or use of the plant, substance or structure for its designed or manufactured purpose
    • the proper storage, handling, decommissioning, dismantling or disposal of the plant, substance or structure
  • are at or near a workplace, and are exposed to the plant, substance or structure, or whose health and safety may be affected by a work activity listed above.
Duty to test

Carry out calculations, analyses, tests or examinations needed to make sure the structure, plant or substance designed is without health and safety risks so far as is reasonably practicable (or arrange the carrying out of such tests).

Note: Where multiple designers are contributing to a project, they all hold responsibilities to carry out their testing duties for the individual parts that they are designing.
Duty to provide information Provide adequate information to people who are provided with the design of the plant, structure or substance. This includes information about:
  • the purpose for which the plant, substance or structure was   designed
  • the results of any calculations, analyses, tests or examinations carried out to make sure the plant, substance or structure is without health and safety risks (in relation to a substance, this includes any hazardous properties of the substance identified by testing)
  • any conditions necessary to make sure the plant, substance or structure is without health and safety risks when used for its designed purpose, or when being handled, stored, constructed, or other foreseeable activities such as inspection, cleaning, maintenance, or repair in relation to:
  • the manufacture, assembly or use of the plant, substance or structure for its designed or manufactured purpose
  • the proper storage, handling, decommissioning, dismantling or disposal of the plant, substance or structure.
On request, make reasonable efforts to give the current relevant specified information on the purpose, results of calculations, analysis, testing and examination, conditions necessary to make sure it is without risk to a person who carries out or is to carry out work activities listed above with the plant, structure or substance.


Table 1: Duties of designer PCBUs (based on the requirements in Section 39 of HSWA)

For further guidance on HSWA, see WorkSafe's special guide Introduction to the Health and Safety at Work Act 2015.

For information on what 'reasonably practicable' means, see WorkSafe's fact sheet Reasonably Practicable.

Other legislation may affect work health and safety (eg the Gas Act 1992 and the Building Act 2004). Where two pieces of legislation apply, the duty holder needs to follow both. HSWA addresses such overlaps by providing that other legislative requirements may be considered when deciding if health and safety duties are being met. However, duty holders may need to do more than what other legislation requires to meet HSWA duties.

Example: An architect that designs a building has duties under HSWA to ensure health and safety, and must also ensure the design complies with the Building Act. Under HSWA the requirements of the Building Act will be taken into account in determining what is required to comply with the architect's HSWA duties.

3.4 Roles and responsibilities in Health and Safety by Design

Throughout the design process of a structure, plant or substance, different people contribute ideas, solutions and knowledge to help manage health and safety risks. PCBUs involved in the design process must consult, cooperate with, and coordinate activities with each other, so far as is reasonably practicable.

In general, the more influence and control a PCBU has over a health and safety matter, the more responsibility it is likely to have.

Figure 3 describes the roles of designers, the manufacturer of the design, the supplier of the manufactured product and the end-user. Adequate information or instructions for safe use should be made available between all the identified parties.

Cllient Designer/design team Manufacturer/Constuctor Supplier End-user
  • commissions the design
  • could be the end user
  • designs the plant, structure, or substance
  • builds or assembles the plant, structure, or substance
  • could be the supplier
  • sells the plant, structure or substance for use in the workplace
  • could be the manufacturer
  • the PCBU that will use the product

Consults, cooperates and coordinates with the designer/design team, so far as is reasonably practicable.

Consults,  cooperates and coordinates with themanufacturer/constructor of their design, so far as is reasonably practicable.

Provides information to the manufacturer/constructor about the purpose ofthe plant, structure or substance, the results of any calculations, testing etc to make sure that risks are minimised so far as is reasonably practicable, and any conditions necessary to make sure that risks are minimised so far as is reasonably practicable (when used for its designed purpose or when being inspected, cleaned maintained or repaired).

On request, provides information as described above to those who will manufacture or supply the structure, plant or substance.

Consults,  cooperates and coordinates with the designer/design team, so far as is reasonably practicable.

 Health and safety risks they identify are referred back to the designer/design team for review.

 On request, provides information as described in Table 1 to those who sell or use the plant, structure or substance in the workplace.

On request, provides information as described in Table 1 to those who use the plant, structure or substance in the workplace.

Should tell manufacturer/ constructor of any faults they become aware of that may create health and safety risks.

Should tell supplier of any faults that may create health and safety risks.

Can ask the supplier or manufacturer/constructor (may be the same PCBU) for information on a structure, plant or substance.

Figure 3: Roles and responsibilities in Health and Safety by Design

4.0 Elements of Health and Safety by Design

4.1 Key principles of Health and Safety by Design

As shown in Figure 4, WorkSafe's approach to Health and Safety by Design outlines five key principles. They are discussed in more detail below.

People

A capable team

Combining great design and risk management can be achieved with a team of capable people. Consultation, coordination and cooperation are essential, particularly between the client and the designer. Teams need strong leadership, technical knowledge, and an understanding of the workplace that products will be used in including how they will be used. A team should be made up of capable people with a variety of different skills and knowledge, and should include workers who will use the structure, plant or substance.

Teams could include:

  • an effective facilitator who has experience in Health and Safety by Design
  • workers and their representatives (eg Health and Safety Representatives)
  • managers
  • designers
  • engineers
  • architects
  • human factors professionals
  • industrial designers
  • software designers
  • supply chain stakeholders
  • health and safety advisors
  • technical experts
  • builders
  • owners
  • insurers.

People who have responsibility for designing work processes and systems have a key role in Health and Safety by Design. This includes a wide range of work health and safety professionals such as:

  • generalist health and safety practitioners
  • occupational  hygienists
  • hazardous substances professionals
  • safety, risk and reliability engineers
  • occupational health physicians and nurses
  • human factors professionals/ergonomists.

A team of capable people may hold these skills:

  • knowledge of work health and safety legislation, good practice guidance and other regulatory requirements
  • an understanding of the intended purpose of the design
  • knowledge of risk management processes
  • knowledge of technical design standards
  • an appreciation of construction methods and their impact on the design
  • the ability to source and apply relevant data on human dimensions, capacities and behaviours.

For further information on competency in Health and Safety by Design, see HSE's Competency Guide:   www.hse.gov.uk/construction/areyou/designer.htm(external link)

Risk management

A lifecycle approach

Choosing inherently safer and healthier options should be the initial consideration when selecting which solution or technology to apply, even before entering the design process. When in the design process, Health and Safety by Design is most effective when applied at the earliest stage. Health and Safety by Design principles should be applied throughout the lifecycle of the the thing being designed – from the concept through to decommissioning and disposal.

The lifecycle encompasses design, planning, assembly, installation, construction, manufacture, commissioning, use, handling, cleaning, maintenance, inspection, repair, transport, storage, dismantling, demolition, or carrying out any reasonably foreseeable activity/work for a purpose for which it was designed.

Procurement

Health and Safety by Design principles should be embedded throughout the procurement  process.

For example:

  • consult with end user representatives in pre-design or early design phases
  • choose designers, contractors or consultants who are proven and able to deliver key Health and Safety by Design principles
  • ensure that Health and Safety by Design expectations (evidence, standards, documents, communications etc) are included in procurement and contract processes
  • choose materials and products based on Health and Safety by Design considerations
  • bring suppliers into the consultation and design process to collectively engineer or design solutions.

Figure 5 shows the different lifecycle stages of a structure, plant or substance.

[image] Typical lifecycle of a product.

Figure 5: Typical lifecycle of a product
A risk management approach

Risks to health and safety arise from people being exposed to hazards (anything that can cause harm). This includes workers and others.

Designers must eliminate health and safety risks arising from work so far as is reasonably practicable. If it's not practicable to eliminate, they must minimise risks, so far as is reasonably practicable.

Designers should take a systematic approach when identifying and managing work risks that are within their ability to influence or control. Figure 6 outlines an approach that can be taken.

[image] Figure 6. A risk management approach.

Figure 6: A risk management approach

Seek the views of your workers and their representatives when assessing work risks or making decisions about ways to manage risk. Your workers will have operational day-to-day knowledge that will be invaluable.

Key information about identified risks and action taken or required to control them should be recorded and transferred from the design phase to those involved in later stages of the project lifecycle. Communicating this information to other duty holders will make them aware of any residual risks and reduce the likelihood of safety features incorporated into the design being altered or removed.

Wherever possible, design safety reviews should involve the people who will eventually construct, manufacture or maintain the structure, plant or substance.

If this is not possible, the client and designer should include people with knowledge and experience in the construction and maintenance processes in the design safety reviews. Their expertise will help with identifying health and safety issues which may have been overlooked in the design.

Designers can use the hierarchy of controls (Figure 7) to help them work out the most effective control measures, so far as is reasonably practicable. Table 2 describes the types of control measures.

[image] A chart showing the types of control measures and their effectiveness.

Figure 7. Hierarchy of controls

[image] Table outlining the different control measures and examples.

Table 2: Types of control measures.

When considering risk management, designers should think about:

  • capability of workers who will use the product
  • control measures that protect multiple people at once.
  • Risks must be eliminated so far as is reasonably practicable. If a risk can't be eliminated, it must be minimised so far as is reasonably practicable.
  • Risk management is not just hazard spotting. Risk management involves identifying and then assessing which work risks to deal with. Risk has two components – the likelihood that it will occur and the consequences (degree of harm) if it happens. To manage risk, you can reduce how serious the harm is if it does occur and/or reduce the chances of it occurring, or ideally both.
  • Check if there are widely used control measures (eg industry standards) for that risk. However, just because something is a common practice doesn't mean that it's the most reasonably practicable option. You should focus on the most effective control measures for the risks.
  • The management of risk needs to be appropriate/proportionate for the scale of the risk. This means risks with potentially significant consequences (eg chronic ill-health, serious injury, and death) may require more effort and resources to determine the most effective way to manage the risk.
  • You may need to use multiple control measures to adequately deal with a given risk.

For more advice on managing risks, see WorkSafe's quick guide Identifying, Assessing and Managing Work Risks.

The following tools and techniques may be useful for identifying and assessing risks at the design stage.

  • HAZOP: Hazard and operability review
  • HAZOP: Computer/Control  HAZOP
  • HAZOP:  Electrical HAZOP
  • HAZID: Hazard identification
  • ENVID: Environmental hazard identification
  • HAZAN: Hazard analysis
  • FMEA: Failure mode and effects analysis
  • ETA: Event tree analysis
  • FTA: Fault tree analysis
  • LOPA: Layers of protection analysis
  • MSRA: Machine safety risk assessment

The risks that designers of structures, plant and substances may encounter and possible control measures are discussed in Sections 5, 6 and 7 of these guidelines.

Quality management systems

Good documentation and communication

Health and safety aspects of the design should be reflected in the requirements of contract documents for the construction/manufacture stage and help  with the selection of suitable and competent contractors for the project. Consultation, cooperation and coordination are an important part of quality management.

Designers must provide adequate information to people who will be using the design. Information about identified health and safety risks, how they were assessed during the design process, and the control measures used should be documented, and applicable standards and decision pathways recorded throughout  the  design process.

Providing this information to others involved later in the lifecycle is necessary to make them aware of any leftover risks and the methods used to minimise risk. This includes training needed at any stage of the structure, plant or substance's lifecycle.

Points for designers to consider when providing information include:

  • making notes on  drawings
  • providing information on:
    • significant hazards, hazardous substances or flammable materials
    • heavy or awkward prefabricated elements likely to create handling risks
    • features that create access problems
    •  temporary work required to construct or renovate the building as designed
    • features of the design essential to safe operation
    • methods of access where normal methods of securing scaffold are not available
    • any parts of the design where risks have been minimised but not eliminated
    • providing risk registers that describe the significant risks identified alongside the mitigation measures adopted or proposed to manage the risk.
Information formats
Design safety report

One method of communicating specific health and safety information relating to the design of a structure/plant is by providing a Design Safety Report.

The Design Safety Report should include information about:

  • the purpose of the structure/plant as communicated by the client in the project brief
  • the parties consulted in undertaking the design
  • the hazards and risks identified during the design process, and control measures incorporated into the design, specifically in relation to:
    • any hazardous materials specified in the design
    • any unusual or atypical features requiring specific attention during construction and manufacture
    • any features of the design which present specific risks
    • the recommended control measures for any foreseeable activities (eg operation, maintenance, repair, dismantling, demolition, disposal) to be carried out during the life of the structure/plant when used for its intended purpose.
Records: Work health and safety file

The development of a work health and safety file (containing all relevant information for a structure/plant) will assist the designer to meet the duty to provide information to others. It could include copies of all relevant health and safety information the designer prepared and used in the design process, such as the Design Safety Report, risk register, product technical statements, safety data sheets, manuals and procedures for safe maintenance, dismantling or eventual demolition.

Consulting your workers

If you are:

  • commissioning a new  workplace
  • commissioning a new piece of plant, or
  • refurbishing your existing workplace,

you must consult with your workers who will be using the workplace or plant. Their health and safety may be affected by the new design.

Frequent monitoring and review

Ongoing monitoring and review throughout design and the lifecycle improves outcomes and allows for variation as new information arises, such as unexpected risks. It will also confirm whether the Health and Safety by Design intent is being achieved. Change management processes will be necessary.

Here are some ways you can monitor and review your control measures:

  • Monitor the effectiveness of all steps of the risk management process. This is important for continuous improvement. Monitor risks and the effectiveness of control measures. Make sure that control measures have not introduced any new risks, and that control measures are effectively managing the risks.
  • On-going review ensures that the data obtained through monitoring is available for feedback into the system.
  • Make sure that the safety recommendations and residual risks within the design are documented for users 'downstream' in the lifecycle.
  • Take steps to make sure that essential modifications and maintenance are carried out and documented for future users.
  • Designs or redesigns should be continually monitored and adjusted to adapt to changes in the workplace. Make sure that new information is used to improve design.
  • As the design progresses and design decisions become more fine-tuned and detailed, there are still opportunities for managing risks. Wherever possible, design safety reviews should involve the people who will eventually construct the structure, plant or substance. If this is not possible, the client and designer should include people with the right knowledge and experience.

Their expertise will assist in identifying health and safety issues which may have been overlooked in the design. Peer review of design and risk assessment from industry/professional groups is encouraged. This approach can encourage collaboration and professional  development.

Change management4

A robust change management process based on good training and awareness should be implemented and maintained throughout the entire asset life cycle.

A formal change approval process should be in place, and this should specifically require any health and safety implications to be considered. For Health and Safety by Design, considerations may include questions such as:

  • Does the change impact on the design intent?
  • Does the change impact on the design risk register?
  • Does the change affect an item identified as a safety or health risk mitigation?
  • Does the change challenge the safe design envelope?
  • Does the change introduce new risks?
  • Does the change result in excessive schedule pressure that may compromise the quality of deliverables?
  • Does the change impact on the methodology?
  • Does the change impact on the risk register?
  • Does the change require changes to organisational  structures?
  • Does the change require changes to work practices, such as moving to an outsourced model for maintenance, engineering or project management?

4 Adapted with permission from the Electricity Engineers Association Safety in Design (Guide) 2016.

5.0 Specific considerations when designing structures

5.1 Designing structures

This section provides information to designers of structures. A designer of structures is a PCBU whose profession, trade or business may involve them:

  • preparing sketches, plans, calculations, specifications, instructions or drawings for a structure, including variations to a plan or changes to a structure
  • making decisions for a design that may affect the health or safety of persons who fabricate, construct, occupy, use or carry out other activities in relation to the structure.

PCBUs that design and work with structures could be:

  • architects, building designers, engineers, building surveyors, interior designers, landscape architects, town planners and all other design practitioners contributing to, or having overall responsibility for, any part of the design (eg drainage engineers designing the drain for a new subdivision)
  • building service designers, engineering firms or others designing services, including the design of seismic restraint systems, that are part of the structure such as ventilation, electrical systems and permanent fire extinguisher  installations
  • contractors carrying out design work as part of their contribution to a project (eg an engineering contractor providing design, procurement and construction  management services)
  • temporary works engineers, including those designing formwork, falsework, scaffolding and sheet piling
  • persons who specify how structural alteration, maintenance, demolition or dismantling work is to be carried out.

For the purposes of these guidelines, 'structures' means anything that is constructed, whether fixed or moveable, temporary or permanent, and includes:

  • buildings, masts, towers, framework, pipelines, quarries, bridges, and underground works (including shafts or tunnels)
  • any component or part of a  structure.

Design includes:

  • the design of any part of the structure
  • the alteration or modification of a design.

Design output includes:

  • drawings in any form
  • design detail
  • design instruction
  • scope of works documents relating to the structure.

The safe design of a structure will always be part of a wider set of design objectives, including practicability, performance, aesthetics, cost and functionality. These sometimes competing objectives need to be balanced in a manner that does not compromise the health and safety of those who work on or use the structure over its life, which includes the maintenance and/or demolition of the structure.

5.2 Systematic steps for designing structures

Designing structures is a process with a series of steps. These are separated into three distinct phases, which are explained in more detail below:

  • pre-design phase
  • conceptual and schematic design phase
  • design development phase.

Once risks have been identified, designers need to work out how they will manage them.

Pre-design phase

Figure 8 illustrates what is involved in the pre-design phase, starting with identifying the purpose of the structure:

[image] figure showing the different parts of the pre-design stage.

Figure 8: pre-design phase
Consultation

The client should prepare a project brief that includes the safety requirements and objectives for the project. This will create a shared understanding of safety expectations between the client and designer.

The client should give the designer all available information relating to the site that may affect health and safety.

Designers should ask their clients about the types of activities likely or intended to be carried out in the structure, including the tasks of those who maintain, repair, service or clean the structure as part of its use.

Research

Information can be found from various sources to help with identifying, assessing and managing risks, including:

  • HSWA and building laws, technical standards and WorkSafe or industry guidance
  • industry statistics regarding injuries and incidents
  • hazard alerts or other reports from: relevant statutory authorities, unions and business associations, specialists, professional bodies representing designers, and engineers' research and testing done on similar designs.

Table 3 below illustrates some possible information sources for identifying hazards.

Step Possible techniques
Initial discussions

Get information on the:

  • purpose of the structure, including plant, ancillary equipment and  tasks
  • industry injury profile and statistics and common risks and health and safety issues
  • guidance from health and safety authorities and relevant industry associations, and standards
  • known hazards and the consultation arrangements between the client and designer/design team.
Pre-design preliminary risk analysis

Useful techniques may include the client doing a combination of these things:

  • holding workshops and discussions with people using or working on similar structures within the client company, including health and safety representatives
  • holding an onsite assessment of an existing similar structure with feedback from its users
  • researching information on similar structures, their associated hazards and relevant sources and stakeholder groups, then completing an analysis for their own design needs
  • holding workshops with experienced people who will construct, use and maintain the new structure
  • holding workshops with specialist consultants and experts in the health and safety risks
  • using BIM (building information modelling) and other forms of modelling to view the physical and functional characteristics of the proposed structure.

The Ministry of Business, Innovation and Employment (MBIE) website has some useful information about BIM and how this could be used throughout the design process. The use of digital information and modelling software applications like BIM in design development and delivery enhances the designer's ability to anticipate, spot and foresee hazards and risks in the design. Designers can use these applications to enable locations, structures and plant to be accurately visualised, sequences of activity to be realistically demonstrated and construction programmes simulated.

Determine what risks are 'in-scope'  Workshops/discussions to determine which risks are affected, introduced or increased by the design of the structure.

Table 3: Information sources for identifying risks

Conceptual and schematic design phase

Risk identification should take place as early as possible in this phase. It is important that the risk identification is systematic and not limited to one or two people's experiences of situations.

Broad groupings of risks should be identified before design scoping begins (Appendix B of these guidelines provides an indicative checklist of issues that should be considered). The designer and others involved should then decide which risks are 'in scope' of the steps of the risk management process, and should be considered in the design process. A risk is 'in scope' if it can be affected, introduced or increased by the design of the structure.

A system of work may also be classed as a risk if it is part of the construction method or intended use of the structure. The nature of the structure should also be taken into account.

Site of structure

Potential design issues that may cause health and safety risks are:

  • how close the structure is to nearby properties or roads
  • what the surrounding land is used for
  • special clearances needed for construction equipment
  • existing structures that may need to be   demolished
  • nearby underground or overhead services
  • nearby traffic flow
  • condition of the work site
  • safety of the public near the work site
  • possible soil contamination and site stability.
Systems of work

Systems of work that could pose health and safety risks are:

  • rapid construction techniques such as  prefabrication
  • dangerous materials that are used in construction
  • other work in the area
  • vehicles and equipment used where there are  pedestrians
  • restricted access for building and plant maintenance
  • manual tasks that could cause injuries and health problems
  • exposure to violence
  • technical and human factors, including how the structure could be misused
  • site access for construction workers and material
  • storage, handling or work with high energy and health hazards.
Environmental or work conditions
  • adverse natural events such as cyclones, earthquakes and  floods
  • poor ventilation or lighting
  • exposure to extremes of temperature
  • high noise levels
  • poor welfare facilities.
Spatial planning and features Appropriately sized amenities and facilities, including access, egress, space to perform tasks, fall prevention, confined spaces, surface treatments, sharp edges, height of features, roof pitch, material durability, site security, and traffic management.
Incident mitigation The risks following an unexpected event or emergency due to inadequate egress, siting of assembly areas, and inadequate emergency services access.

Table 4: Framework for the preliminary risk identification

Design development phase

In this phase, the designer converts concepts for the structure into detailed drawings and technical specifications. They decide on control measures and prepare construction documentation. At that stage, the design is complete and can be handed to the client.

Figure 9 illustrates what this phase involves.

[image] figure showing the stages of the design development phase

Figure 9: The design development phase

Check if there are widely used control measures (eg industry standards) for that risk. However, just because something is a common practice doesn't mean that it's the most reasonably practicable option. You should focus on the most effective control measures for your circumstances.

Implement solutions from recognised standards

The primary legislative provision governing the design of buildings and structures in New Zealand is the Building Act and the New Zealand Building Code (Building Code). In addition, there are technical and engineering guidelines and standards produced by other government agencies, Standards New Zealand and relevant professional bodies. The main focus is to make sure that structures meet acceptable standards for structural soundness, safety, health and amenity.

The design should include technical provisions for:

  • structural soundness
  • fire spread within and between buildings
  • building occupant entry and exit
  • fire-fighting equipment
  • presence or use of hazardous substances
  • smoke hazard management and
  • emergency services access to buildings.

Health and safety amenity aspects such as ventilation, lighting, Legionella controls, sanitary facilities and damp and weatherproofing measures should also be covered.

For information about preventing Legionnaires' disease see WorkSafe's guidance Preventing Legionnaires' disease from cooling towers and evaporative condensers.

The Building Code refers to New Zealand and Australia/New Zealand Standards, but designers should be aware that these may not adequately manage risks

if applied to a situation outside that contemplated in the Standard or if the Standard is out-dated. The Building Code also does not provide guidance for some specialised structures such as major hazard facilities (eg refineries).

Assessing risk

A risk assessment looks at what could happen if someone is exposed to a hazard, and how likely this is to happen. It is important that those involved in a risk assessment have the information, knowledge and experience of the work environment to make informed decisions.

If similar tasks or processes apply for a number of projects, a general risk assessment model may be appropriate. However, the designer is still responsible for ensuring that the generic assessment is valid for the project, before deciding to adopt it.

Risk assessment methods for assessing design safety may include:

  • fact finding to determine possible health and safety risks
  • testing design assumptions to make sure that no aspect of it is based on incorrect beliefs or anticipations on the part of the designer
  • testing of structures or components specified for use in the construction, end use and maintenance
  • talking with key people who have the knowledge to control or influence the design (such as the architect, client, construction manager, engineers, project managers, and health and safety representatives)
  • talking with key people who have the knowledge to identify and assess risks
  • when designing for the renovation or demolition of existing buildings, reviewing previous design documentation or information recorded about the design structure and any alterations to address health and safety   concerns
  • talking with professional industry and worker associations, and local authorities, who could help with risk assessments for the type of work and workplace
  • ensuring you don't fall into traps in risk assessment such as:
    • carrying out a risk assessment to attempt to justify a decision that has already been made
    • using a generic assessment when a site-specific assessment is needed
    • carrying out a risk assessment using bad practice
    • only considering the risk from one activity
    • not involving a team of relevantly skilled people in the assessment or not including workers with practical knowledge of the process/activity being assessed
    • ineffective use of consultants
    • failure to identify all risks associated with a particular activity
    • failure to fully consider all possible outcomes
    • inappropriate use of data
    • inappropriate use of risk criteria (the measures you compare risk against to decide if it's acceptable or not)
    • no consideration of 'reasonably practicable' or further measures that could be taken
    • inappropriate use of cost benefit analysis
    • using 'Reverse Reasonably Practicable' arguments (ie using cost benefit analysis to attempt to argue that it is acceptable to reduce existing health and safety standards)
    • not doing anything with the results of the assessment
    • not linking hazards with risk controls.

When thinking about which control measures to  implement:

  • look specifically at risks that a capable user would not be expected to be aware of
  • look at where leftover risks remain, and make sure the builder and other relevant stakeholders are aware of these
  • look at the interaction of hazards in the assessment of their risks and implementation of control  measures
  • assess alternative control measures for their suitability.

Table 5 outlines the design process

Step Possible techniques By whom
Identify solutions from regulations, good practice guidance and recognised standards

Talk with all relevant people to figure out which risks can be addressed with recognised standards.

Plan the risk management process for other hazards.

Designer led.

Health and Safety by Design team input.

Client approval of decisions.

Apply risk management techniques

Further detailed information may be needed on risks, for example by:

  • using checklists and referring to guidance material
  • job/task analysis techniques.

A variety of risk assessment measures can be used to check the effectiveness of control measures. These may be qualitative or quantitative.

Scale models and talking with experienced industry members may be necessary to come up with solutions to longstanding health and safety issues.

Designer led.

Client provides further information as agreed in the planned risk management  process.

Health and Safety by Design team input.

Discuss design options Take into account how design decisions influence risks when discussing control measure options.

Designer led.

Client contributing.

Health and Safety by Design team input.

Design finalisation

Check that the evaluation of control measures is complete and accurate.

Prepare information about risks to health and safety for the structure that remain after the design process.

Designer led.

Client and designer agree with final result.

Health and Safety by Design team input.

Potential changes in construction stage Make sure that changes which affect design do not increase risks.

Construction team in consultation with designer and client.

Health and Safety by Design team input.

Table 5: The design process

Design considerations

There are different design options to manage risks throughout a structure's lifecycle. Figure 10 illustrates these, and examples are given below.

[image] chart showing design considerations for structures.

Figure 10: Design considerations for structures.

Design for safe construction

Below are some examples of control measures relating to the construction of a structure:

  • providing enough clearance between the structure and overhead electric lines by burying, disconnecting or re-routing cables before construction  begins
  • designing components that can be made off-site or on the ground – this reduces falls from heights or being struck by falling objects
  • designing parapets to a height that complies with guardrail requirements
  • this eliminates the need to construct guardrails during construction and provides future edge protection for work at heights
  • using continual support beams for beam-to-column double  connections
  • this will provide continual support for beams during erection, and will reduce the risk of falls due to unexpected vibration, unexpected construction loads and misalignment
  • designing and constructing permanent stairways to help prevent falls and other hazards associated with temporary stairs and scaffolding
  • reducing the space between roof trusses and battens to reduce the risk of internal falls during roof  construction
  • choosing construction materials that are safe to handle
  • designing in aids for lifting during construction (eg provision of lifting lugs to roof-top air conditioning plants)
  • limiting the size of pre-made wall panels where site access is restricted, including glass panels used for cladding or other purposes
  • selecting building materials, paints or other finishes that emit low levels of dangerous vapours
  • indicating, where practicable, the position and height of all electric lines to help with site safety procedures
  • maintaining safe smooth access, so far as is reasonably practicable, throughout the site for separately moving people, materials and vehicles
  • designing components that can be partially finished off-site or prefabricated (so far as is reasonably practicable) to reduce exposure during construction to substances hazardous to health such as dusts, paints, glues etc.

Design to facilitate safe use

Consider the intended function of the structure, including the likely systems   of use, and the type of machinery and equipment that may be used.

Consider whether workers may be exposed to specific hazards, such as manual tasks in health facilities, workplace violence in law enforcement facilities,  or dangerous  goods storage  in warehouses.

Below are some examples of how risks relating to a structure's use can be managed by:

  • designing traffic areas to separate vehicles and pedestrians, including adequate access for delivery of construction material and plant to the site
  • designing in access for maintenance purposes (eg fixed stairs to a machine room)
  • using non-slip materials on floor surfaces in areas exposed to the weather or dedicated wet areas
  •  providing enough space within the structure to safely install, operate and maintain plant
  •  providing enough lighting for intended tasks in the structure
  • designing spaces in which workers can use mechanical plant or tools to reduce manual task risks
  • designing access to structures that will serve a specific purpose, such as wide corridors for wheelchairs in hospitals
  • designing effective noise barriers and acoustical treatments to walls and ceilings
  • designing the structure to isolate noisy plant
  • designing floor loadings to accommodate heavy machinery that may be used in the  structure
  • clearly indicating on documents the design loads for different parts of  the structure
  • designing for specific task demands
  • considering for potential future use
  • designing to accommodate the physical characteristics of different users
  • using sub-floor heating on floor surfaces that are exposed to moisture from weather or tracked moisture to enable them to dry more easily
  • providing detailed plans and instructions that are comprehensive and understandable to enable safe use of designed accessways, access systems  and  their components.

Design for safe maintenance

Below are some examples of how risks relating to cleaning, servicing and maintaining a structure can be managed by:

  • designing the structure so that maintenance can be performed at ground level or safely from the structure. For example, positioning air-conditioning units and lift plant at ground level, designing inward opening windows, and integrating window cleaning bays or gangways into the structural frame
  • designing features to avoid dirt or moisture traps
  • designing and positioning permanent anchorage and hoisting points into structures where maintenance needs to be completed at height
  • designing safe access (such as stairways or fixed ladders) and enough space to complete structure maintenance activities
  • eliminating or minimising the need for entry into confined spaces
  • using long-life components such as LED lighting that don't require frequent replacement
  • using durable materials that do not need to be re-coated or treated.

Design can involve the alteration of an existing structure. Modification may mean partial or full demolition. At this stage, designers should consult with key stakeholders to manage risks, and follow the key principles of Health and Safety by Design. Anyone who modifies a design is also a designer.

Demolition and dismantling

A structure should be designed so it can be demolished using existing techniques. The designer should provide information so that potential demolishers can understand the structure, load paths and any features incorporated to help with demolition. They should also provide information on any features that require unusual demolition techniques or sequencing.

Designers of new structures should design facilities such as lifting lugs on beams, or columns and protecting inserts in pre-cast panels, so they can be used for disassembly. Materials and finishes specified for the original structure may require special attention at the time of demolition, and any special requirements for the disposal and/or recycling of those materials or finishes should be described in the risk assessment documentation.

There are general risks that should be considered when designing structures. Designers should consider as many factors as possible to manage the health and safety risks they present. Appendix B outlines some common risks, and design considerations to manage them.

5.3. Reviewing control measures

As the design progresses and design decisions become more fine-tuned and detailed, there are still opportunities for managing risks. At various points in the design process, designers should review design solutions to confirm the effectiveness of control measures and if necessary, redesign to eliminate the risks so far as is reasonably practicable.

Wherever possible, design safety reviews should involve the people who will eventually construct the structure. If this is not possible, the client and designer should include people with knowledge and experience in the construction and maintenance processes in the design safety reviews. Their expertise will assist in identifying safety issues which may have been overlooked in the design.

Health and safety aspects of the design should be reflected in the requirements of contract documents for the construction stage and assist in the selection of suitable and competent contractors for the project.

On completion of construction, the effectiveness of Health and Safety by Design should be evaluated. This will help the designer to identify the most effective design practices and any design innovations that could be used on other projects. Feedback from users to help designers in improving their future designs for structures may be provided through:

  • post-occupancy evaluations for buildings
  • defect reports
  • accident investigation reports
  • information regarding modifications
  • user difficulties
  • changes from intended conditions of use.

Section 4 of these guidelines outlines some ways that designers can review control measures to make sure that risks are being effectively managed.

6.0 Specific considerations when designing plant

6.1 Designing plant

This section provides information to designers of plant to be used at work.

Plant includes:

  • machinery
  • equipment
  • appliances
  • containers
  • implements
  • tools and components.

Examples of plant are illustrated in Figure 11 below.

[image] chart showing examples of plant.

Figure 11. Examples of plant

This section also applies to the design of structures where items of plant are designed as a structural component or are assembled to form a structure.

6.2 Systematic steps for designing plant

Designing plant is a process with a series of steps. These are separated into two distinct phases, which are explained in more detail below:

  • pre-design and concept development phase
  • design development phase.

Once risks have been identified, designers need to work out how they will be managed.

Pre-design and concept development phase

This phase involves:

  • deciding on the intended use of the plant, its functions and limitations
  • identifying the roles and responsibilities for the project
  • establishing co-operative relationships with clients, manufacturers and users of the plant, including those who maintain and repair the plant
  • researching and consulting to help with identifying hazards, and identifying and managing risks.
Intended use of plant

Designers can decide on the intended use of the plant, including its functions and limitations, by looking at:

  • the expected place of use
  • intended functions and operating modes
  • safe use requirements, including reasonably foreseeable misuse
  • planned service life
  • relevant standards and specifications
  • possible malfunctions and faults
  • testing, maintenance and repair requirements
  • the people interacting with the plant
  • other products interacting with or related to the plant.
Identifying health and safety risks

The first step in the risk management process is to identify all risks, so far as is reasonably practicable. Risk identification should be done as early as possible in the concept development and design phases. Risks relating to plant are often caused by the plant itself, and how and where the plant is used.

Risks may be identified by looking at the workplace and how work is carried out. Designers could talk to workers, manufacturers, importers, suppliers and health and safety specialists, and review relevant information, records and incident reports.

Table 6 lists things to consider when looking for plant risks.

Table 7 shows examples of potential plant risks and phases of the plant lifecycle after the design has been completed where people might be exposed to plant hazards.

Things to consider to identify plant risks
Risks
  • Can the plant cause injury or ill health from poor design?
  • Can the plant cause injury from entanglement, crushing, trapping, cutting, stabbing, puncturing, shearing, abrasion, tearing or stretching?
  • Can the plant create hazardous conditions from pressurised content, electricity, noise, radiation, friction, vibration, fire, explosion, temperature, moisture, vapour, gases, dusts, mists, fumes, ice, or hot or cold parts?
  • Can the plant cause injury from lack of guarding of moving  parts?
  • Can the plant cause injury as a result of unexpected  start-up?
Suitability
  • Is the plant fit for its intended purpose? What is likely to happen if it is used for a purpose other than the intended purpose?
  • Are the materials used to make the plant suitable?
  • Are plant accessories fit for their intended purpose?
  • Is the plant stable? Could it roll over?
  • If the plant is intended to lift and move people, equipment or materials, is it capable of doing this?
Access
  • Is access to the plant necessary when installing, using and maintaining the plant or in an emergency?
  • Can workers access the plant safely without being injured by the plant or slips, trips and falls (eg by a walkway, gantry, elevated work platform or fixed ladder) or having to enter a dangerous environment to access plant?
Location
  • Does the plant affect the safety of the area where it will be located?
  • Does the location affect the plant in a way that could impact health or safety (eg environmental conditions, terrain, airborne hazards and work area)?
  • Will there be people or other plant nearby? What effect would this have?
Systems of work
  • Do the systems of work for the plant create risks?
  • Does the plant's safety depend on the competency of its users?
  • Will users and others working near the plant need relevant training, information, instruction and supervision?
Unusual situations
  •  What unusual situations or misuse could occur?
  • What would happen if the plant failed? Would it result in loss of contents, loss of load, unintended ejection of work pieces, explosion, fragmentation or collapse of parts, release of substances hazardous to health, or other hazardous exposures?
  • Is it possible for the plant to move or be turned on accidently?

Table 6. Things to consider when identifying plant risks.

Potential risks Phases of plant lifecycle
  • mechanical (eg crushing, cutting, trapping, shearing and high pressure fluids)
  • electrical
  • thermal
  • noise
  • vibration
  • radiation – light, heat, electric fields, magnetic fields, radioactivity
  • substances hazardous to health including chemicals, chemical by-products
  • biological exposures (eg bacteria, molds, viruses)
  • slipping, tripping and falling
  • manual handling
  • confined spaces
  • hazards resulting from a combination of the above.
  • manufacture
  • storage
  • packing and transportation
  • unloading and unpacking
  • assembly
  • installing
  • commissioning
  • using
  • cleaning and adjustment
  • inspection
  • planned and unplanned maintenance or repair
  • decommissioning
  • dismantling
  • disposal and recycling.

Table 7: Examples of plant risks and phases of the plant lifecycle

6.3. Design phase

Figure 12 illustrates what is involved in this phase.

[image] the design phase

Figure 12. The design phase

Check if there are widely used control measures (eg industry standards) for common risks. However, just because something is a common practice doesn't mean that it's the most reasonably practicable option. You should focus on the most effective control measures. So before considering applying a widely used control measure, consider whether it will be effective in managing the risk in your situation (eg when working at height, will using mobile work platforms, rather than step ladders, more effectively minimise the risk?).

Technical standards

A plant designer may use technical standards, or a combination of standards and engineering, design, or ergonomics principles relevant to the design requirements (as long as the design meets regulatory requirements). Engineering principles could include mathematical or scientific procedures outlined in an engineering reference or standard.

Testing and examining plant

The designer should carry out any analysis, testing or examination that may be necessary to make sure the plant is without health and safety risks so far as is reasonably practicable.

Testing may include developing a prototype  to:

  • simulate the normal range of operational  capabilities
  • test design features to ensure 'fail-safe' operation
  • measure imposed stresses on critical components to make sure maximum design stresses are not exceeded
  • test critical safety features under both normal and adverse operational conditions
  • develop overload testing procedures to ensure plant safety when plant is misused.

Records of tests and examinations must be kept by the designer.

For more information on duties for designers, see Section 3.3 of these guidelines.

There are several different factors to think about when looking to identify and manage risks throughout plant's lifecycle. Figure 13 illustrates some of these, and they are explained in further detail below.

[image] chart outlining design considerations

Figure 13. Plant design considerations.
Designing plant which is safe to use

A designer should consider:

  • the required skill levels to manufacture, install, commission, use or maintain the plant
  • the complexity of functions a user can be expected to perform
  • the need for and the location of items such as aids, guides, indicators, guards, mounted instruction, signs, symbols, gauges, alarms, dials, screens, switches, emergency stops and name plates to make sure the plant is used correctly
  • making sure plant design is 'fail-safe' to the category, performance and safety level determined by the plant risk assessment
  • the layout of work stations
  • instrumentation needed at each work station or cabin and the layout of the instrumentation
  • devices, tools or control measures the user and support people need in order to carry out their jobs safely
  • the options available to maintain the safety and integrity of the system if the user makes a mistake, or if the plant fails
  • whether the user of the plant can be easily accessed if they need help (eg if emergency rescue of the user is required)
  • environmental conditions that may weaken user performance (eg working in extremes of temperature, humidity)
  • separating people, including the user, from entrapment when using  plant
  • ensuring hazardous fumes, gases or vapours are not able to escape plant, or are directed away from the user if they do escape (eg directing exhaust that contains hazardous fumes, gases or vapours away from the users, or ensuring filtering is in place to reduce the release of hazardous exposure).

Designers should also consider predictable human behaviour. Where user error is likely, higher order control measures such as elimination or substitution should be incorporated into the design.

User characteristics

When designing plant, designers should consider the range of physical and intellectual characteristics of likely users. Things like height, weight, reach and physical ability should be considered. If future user information is available, the designer could tailor the plant design to meet the needs of

specific people, keeping in mind that the people using the plant may change over time.

A designer should:

  • apply ergonomic design principles so risks to health and safety are managed, so far as is reasonably practicable
  • take into account the physical ability of workers including requirements for strength, reach, vision, and hearing
  • consider whether the plant could be misused or how a user's uncontrolled physical movements could impact how the plant operates
  • consider the risks that arise when an unexpected event or emergency happens that impact on the user characteristics.
Human erorr

Human error is not always the result of people being careless. Sometimes workers may want to finish a job quickly or make a task easier. This can lead to workers making decisions that can lead to an increase in health and safety risks.

Workers have a responsibility to take reasonable care for their own health and safety and must take reasonable care that their acts or omissions do not adversely affect the health and safety of others. They must comply with any reasonable instruction and cooperate with any reasonable policy or procedure. Workers should not use unsafe practices or deliberately avoid guarding on plant.

Designers should be aware of the factors contributing to human error when designing plant including:

  • forgetfulness
  • workers' motivation to 'get the job done' or to 'find a better  way'
  • ability to understand information including literacy
  • psychological or cultural environment
  • habit
  • accepted practice
  • fatigue
  • level of training
  • availability of support, help or emergency equipment outside normal work hours.
Reasonably forseeable future

When designing plant, designers should assess the risk of reasonably foreseeable misuse by users, and incorporate appropriate control measures into their design. One way of identifying potential misuse is by reviewing incident reports for similar types of plant, as well as literature reviews and industry reports.

Environmental conditions that the plant will be used in

A designer should consider the risks created by the physical, environmental and operational conditions that plant and its users could be exposed to during its lifecycle. These conditions may include:

  • ice
  • water
  • wind
  • UV and, infrared light
  • dust, mist, gases and fumes
  • lightning
  • temperature and humidity - both high and low
  • positioning of the plant in relation to work flow
  • health hazards (eg noise, vibration, hazardous fumes, gases or vapours created by or around the plant).

A designer can also contribute to minimising the environmental risks by providing instructions to erectors and installers of plant about positioning of the plant (eg by showing how much less noise the plant will emit if it is placed in an open area rather than in a corner where reflection of sound from walls will increase noise levels). If a user is physically uncomfortable using the plant, this may lead to inattention, carelessness, fatigue, or cutting corners which can cause incidents.

Erecting and installing plant

A designer should, so far as is reasonably practicable, make sure health and safety risks arising from erecting and installing plant are managed. These risks may include:

  • working at heights – leading to falls
  • stretching or bending at an unnatural angle – leading to  injuries
  • hazardous exposures during installation or commissioning (eg hazardous gases, fumes, vapours, noise, vibration, light).

Designers should also consider the stability of plant when it is assembled, erected or installed, and whether special supports are required.

Maintenance

A designer's responsibility extends to eliminating or minimising the risks associated with maintaining the plant, so far as is reasonably practicable. Any reasonably foreseeable hazards with future plant maintenance and repair should be identified and designed out.

If the plant needs to be operated during cleaning or maintenance, the designer should design the operator's controls so the plant cannot be operated by anyone other than the person maintaining or cleaning the plant.

Where a worker has to maintain plant, a designer should:

  • design places for adjusting, lubricating and maintaining the plant outside danger zones
  • incorporate interlocks into the design so the plant cannot be activated while maintenance work is carried out in the danger zones
  • design safe entry points, like walkways and guardrails for maintenance or inspection (eg cooling towers or storage silos)
  • pass on relevant information to the manufacturer for inclusion in the manufacturer's instructions for maintenance
  • design parts of the plant where workers move or stand to manage the risk of slips, trips and falls
  • design the plant to manage the risk of accidently touching hot, sharp or moving parts
  • design the plant so that exposure to hazardous substances, or other hazards (eg noise) are minimised during maintenance.

There are general risks that should be considered when designing plant. Designers should consider as many factors as possible to manage the health and safety risks they present. Appendix B outlines some common risks, and design considerations to manage them.

6.4 Design information for the manufacturer

Designers should provide specific information to the manufacturer, so that the plant is manufactured following the design specifications.

They should provide information on:

  • installing, commissioning, using, handling, storing, decommissioning and dismantling the plant
  • hazards and risks associated with using the plant, and the identified control measures that need to be included in the manufacture of the plant
  • testing or inspections to be carried out
  • systems of work and competency of users necessary for the plant to be used safely
  • emergency procedures if there is a malfunction.

If the manufacturer tells the designer there are health and safety issues with the design, the designer should revise the design to take account of these concerns, or they could tell the manufacturer in writing why revisions are not needed.

Designer information that can be provided to the manufacturer is in Table 8.

Manufacturing plant
  • specific conditions relating to the method of manufacture
  • instructions for fitting or refitting plant parts and their correct location
  • instruction where hot or cold parts or material may create a risk
  • specifications of material
  • specifications for components (eg ergonomically designed controls)
  • wiring diagrams
  • specifications for proprietary items (eg electric motors)
  • component specifications including drawings and tolerances
  • assembly drawings
  • assembly procedures including specific tools or equipment to be used
  • manufacturing  processes
  • details of hazards presented by materials during manufacturing
  • safety outcomes for programming.
Transporting, handling and storing plant
  • dimensions and weight
  • handling instructions
  • conditions for storage.
Installing and commissioning plant
  • risks from exposure to dangerous parts before guards are installed
  • lifting procedures
  • plant interacting with people
  • plant interacting with other plant
  • stability during installation
  • the proposed method for installing and commissioning
  • using special tools, jigs, fixtures and appliances necessary to minimise risk during installation
  • concealed installations
  • environmental factors affecting installation and commissioning that may present risk.
Using, inspecting, testing and decommissioning plant
  • intended uses for the plant including prohibited uses
  • operating procedures
  • safe entry and exit
  • requirements for maintenance and repair
  • emergency situations
  • hazardous exposures including hazardous substances, exhausts, light, heat, noise, biological exposures
  • how environmental conditions affect using the plant
  • the results or documentation of tests carried out on the plant and  design
  • de-commissioning, dismantling and disposing of plant
  • known leftover risks that cannot be eliminated or sufficiently minimised by design
  • details of control measures to further minimise the risks associated with plant
  • information on administrative control measures
  • requirements for special tools needed to use or maintain plant.

Table 8: Designer information that can be provided to the manufacturer.

6.5 Design verification of pressure equipment, cranes and passenger ropeways

The Health and Safety in Employment (Pressure Equipment, Cranes, and Passenger Ropeways) Regulations 1999(external link) require the design of this type of plant to be verified before it can be certified and first used.

For plant under these Regulations, the information that the designer should provide to the manufacturer should include the verified drawings and certification.

This provides evidence the plant design has been verified under the Regulations.

A design should only be verified by a competent  person.

In general, people who are competent to verify the design of plant are those who:

  • are employed or engaged by a Recognised Inspection Body, and
  • hold Chartered Professional Engineer Status recognised by the Engineering New Zealand (ENZ) and are deemed competent to carry out design verification (or similar overseas), and
  • have educational or vocational qualifications in an engineering discipline relevant to the design to be verified, and
  • have knowledge of the technical standards relevant to the design to be verified, and
  • have the skills necessary to independently verify that the design was produced following the published technical standards and engineering principles used in the design, and
  • are authorised by a body accredited or approved by the Joint Accreditation System – Australia and New Zealand or an equivalent overseas body to carry out conformity assessments of the design against the relevant technical standards. In New Zealand this body is International Accreditation New Zealand (IANZ).

The design verifier may be in-house or an independent contractor. They should not have been involved in the plant design process unless that PCBU has an accredited and documented quality system in place that has been certified by IANZ (or a body accredited or approved by the Joint Accreditation System – Australia and New Zealand).

6.6 Intended use of plant

The intended use of the plant, including its functions and limitations, can be determined by looking at:

  • the expected place of use (eg environment and supporting surfaces)
  • intended functions and operating modes
  • safe use requirements including reasonably foreseeable misuse
  • planned service life
  • relevant standards and specifications (eg what is produced and materials to be used)
  • possible malfunctions and faults
  • testing, maintenance and repair  requirements
  • the people interacting with the plant
  • other products interacting with or related to the plant.

6.7 Design sources of human error

Poorly designed plant can lead to inadvertent or inappropriate actions from the people using the plant. Examples of these are in Table 9 below.

Untitended outcome Possible causes due to poor design
Inadvertent activation of plant
  • Lack of interlocks or time lockouts.
  • Lack of warning signs against activating equipment under specified damaging conditions.
Errors of judgement, particularly during periods of stress or high job demand
  • Critical displays of information are too similar or too close together, or visually difficult to see.
  • Job requires user to make hurried judgements at critical times, without programmed back-up measures.
Critical components installed incorrectly
  • Design and instructions on installing components are difficult to   understand.
  • Lack of configurations or guides on connectors or equipment.
Inappropriate use or delay in use of operator controls
  • Critical operator controls are too close, similar in design or awkwardly located.
  • Readout instrument blocked by arm when making  adjustment.
  • Labels on operator controls are confusing or missing. Information is too small to see from user's position.
Inadvertent activation of operator controls
  • Operator controls can be activated accidentally.
  • Lack of guards over  critical operator  controls.
Critical instruments and displays not read or information misunderstood because of clutter
  • Critical instruments or displays not in an obvious area.
  • Displays look too similar.
Failure to notice critical signal
  • Lack of acceptable warning to attract user's attention to information.
Plant use results in unexpected direction or response
  • Direction of operator controls conflicts with normal operation
Lack of understanding of procedures
  • Instructions are difficult to understand
Folllowing prescribed procedures results in error or incident
  • Writted prescribed procedures are wrong and have not been checked
Lack of correct or timely actions
  • Available information incomplete, incorrect or not available in time.
  • Response time of system or plant too slow for making the next correct action.
  • Lack of automatic corrective devices with fast fluctuations.
Exceeding prescribed limitations on load or speed
  • Lack of governors and other parameter limiters.
  • Lack of warnings on exceeding  parameters.

Table 9: Design sources of human error

7.0 Specific considerations when designing substances

7.1 What is hazardous substance?

A hazardous substance is any substance with one or more of the following properties, as described in Figure 14.

[image] properties of a hazardous substance

Figure 14. Properties of hazardous substances

In addition, if a substance gains any of the above properties when it comes into contact with air or water, it is considered hazardous.

This section focuses on the design, redesign or modification of a substance.

7.2 Approval of hazardous substances

All hazardous substances that are manufactured in or imported into New Zealand need to be approved under the HSNO Act (Hazardous Substances and New Organisms (HSNO) Act 1996). The approvals are given by the Environmental Protection Authority (EPA). When a substance is approved, controls are applied to manage any risk that may arise during the substance's lifecycle.

The Health and Safety at Work (Hazardous Substances) Regulations 2017 are a set of controls developed for each class of hazardous substance, and for particular phases of a substance's life cycle. They replace the controls set under the HSNO Act 1996. For more information on the Hazardous Substances Regulations 2017, see our hazardous substances section.

Not all substances hazardous to health are covered by the Hazardous Substances Regulations (eg fumes produced as a by-product of heating). However, there is still a requirement to make sure that the hazard is identified and the risk associated with the substance is managed.

7.3 Control measures for managing substances

The specific control measures required by the Regulations may help manage the risks associated with manufacturing, using, handling or storing hazardous substances at work.

Depending on the hazardous properties of the substance these control measures may include specific requirements around:

  • inventories
  • safety data sheets
  • emergency preparation and response plans
  • labelling
  • protective equipment
  • fire extinguishers
  • signage
  • certified handlers
  • compliance certification
  • establishment of hazardous areas
  • secondary containment (bunding)
  • stationary container compliance certification
  • tracking
  • approved filler certification, and
  • controlled substances licences.

A simple way to find out the key controls that apply to a substance is to use the hazardous substances calculator at: www.hazardoussubstances.govt.nz(external link)

Although these control measures apply when the substance is in the manufacture, use, handling or storage phases of the lifecycle, they should be given consideration during the pre-design and design stage, as the control measures are a critical element in the management of risk from the substance.

7.4 Design considerations for substances

The intrinsically hazardous properties of a substance may be unavoidable, if they are integral to the function of the substance at work. However, the principles of Health and Safety by Design should still be applied.

Designers of substances should consider:

  • their understanding of chemistry principles, toxicology and environmental science
  • looking at whether hazardous properties can be removed while still maintaining the functionality and efficacy of the substance
  • looking at whether the toxicity or reactivity of the substance can be managed by varying these things:
    • the molecular weight
    • volatility
    • particle size
    • solubility
    • reactivity
    • thermo-reactivity
    • shape
    • molar mass
  • looking at whether the substance's potential for the following things can be managed through good chemical design:
    • bioaccumulation
    • environmental  persistence
    • receptor binding
  • ensuring that there is reliable, well tested data for all relevant routes of exposures, no observed adverse effect levels or concentrations (NOAEL/ NOAEC) and lowest observed adverse effect levels/concentrations (LOAEL/LOAEC)
  • understanding the process of metabolism or degradation of the substances in the body and in the  environment
  • taking a product stewardship approach – making health, safety and environmental protection an integral part of the life cycle of chemical products, in partnership with others involved in the product.

There are general risks that should be considered when designing substances. Designers should consider as many factors as possible to manage the health and safety risks they present. Appendix B outlines some common risks, and design considerations to manage them.

7.5 Inherently safer substances

When designing and developing safer substances, the designer needs to find a balance between eliminating, then minimising health, safety or environmental risks, and maintaining the effectiveness of the substance. If a less hazardous version of the substance is designed that is not as effective as those currently being used, the health and safety benefits may outweigh this reduction in effectiveness.

So far as is reasonably practicable, the designer should consider what is able to be done to ensure health and safety, taking into account:

  • the likelihood of risk
  • the degree of harm
  • the ways of eliminating or minimising risk and
  • the cost and whether it is grossly disproportionate to the risk being considered.

Information on how PCBUs can make safer choices around substances to use is available in our substances guidance section.

More information on how designers can communicate, cooperate and coordinate with other relevant stakeholders is outlined in Section 3 of these guidelines.

Information on safe substitution of substances is also available from the following resources:

  • www.osha.gov/dsg/safer_chemicals/basics.html(external link)

  •  www.ontario.ca/document/ontario-toxics-reduction-program-reference-tool-assessing-safer-chemical-alternatives-0(external link)

  • (external link) Minimising chemical risk to workers' health and safety through substitution, European Commission Directorate-General  for  Employment,  Social Affairs and Inclusion Unit Health, Safety & Hygiene at Work  (2012).

8.0 Case studies

8.1 NZTA's Waterview connection project

Set the scene

This was the largest civil engineering project in New Zealand at the time of construction between 2011-2017. It comprised:

  • 5 km long, 3-lane (each way) motorway comprising 35 kilometres of lanes
  • two 2.4 km long 13.1 m (ID) diameter bored tunnels and ventilation buildings
  • six road bridges – 1,700 m total length
  • two long span footbridges and several smaller structures
  • over 3 km of retention structures up to 30 m high
  • extensive urban improvements and landscaping
  • 5+ years construction period
  • operations and maintenance responsibilities for 10 years
  • delivered to NZTA for $1.4 billion capital cost.

[image] people in hard hats and orange jackets watching tunnel boring machine breakthrough a tunnel

TBM Breakthrough at the Southern Portal

What went wrong and what went right?

Safety in Design (SiD) was implemented on the project from the tender design phase. It was a formal process that was documented in the design management plan and applied throughout the design and delivery period.

A risk based approach was used, where workshops were held in the early stages of design with participation from design, construction and operations personnel. This was so that a range of knowledge and experience was present and consideration was given to the full life cycle. The workshops identified safety-related risks for all elements of the project that could be mitigated, to at least some degree, through smart design. An SiD register was maintained to capture and monitor the treatment of those safety risks throughout the design phase, and also to capture the transfer of any residual risk at the end of design to construction and ultimately to operations. Design reports also specifically documented SiD considerations and treatment.

This approach was successfully applied across the project with a number of key design decisions driven by safety considerations.

Two examples of SiD related outcomes from the project:

  1. Selection of the tunnelling method and the decision to go with a Tunnel Boring machine (TBM) was driven in large part by risk mitigation and safety considerations. The TBM method meant all workers and equipment were shielded within the TBM shield or permanent lining which removed the risk of exposure to collapse or inundation. The TBM method itself also reduced the risk of collapse and inundation from occurring, mitigating risk to surface infrastructure and facilities

[image] tunnel boring machine with man walking past.

Alice the TBM
  1. The southbound motorway approach into the northern portal of the tunnel has two lanes coming from each direction (east and west) merging into three lanes into the tunnel (ie three lanes merging into four lanes). This means the outside lane from each direction has to merge with the one coming from the other direction. The tunnel approach is all on elevated viaduct and comprises a merging ramp approaching from each direction with concrete side barriers. The barriers meant visibility to traffic on the adjacent merging ramp would have been restricted until very late in the merge process. A decision was made to improve the pre-merge visibility by using barriers on the merge side of the ramps with a rail on the top to reduce the height of concrete and therefore improve cross ramp visibility (by making the tops of the barriers 'see-through'). Furthermore, where the two ramps connected, an additional piece of infill slab was constructed that allowed the barriers to be removed completely.  This  further improved visibility between  traffic in the merging two lanes.

[image] southbound motorway merging into the northern motorway surrounded by green setting.

Southbound merge approach into the northern

[image] close up of motorway infill slab and see through to pillars and ground below.

Close-up of infill slab and 'see through'

What lessons can we take from this project and share with the industry?

  • Implementation of a SiD process early in the design period means real safety improvement outcomes can be achieved.
  • Participation of people from differing design disciplines as well as beyond the overall design discipline, such as constructors and operations personnel, is extremely beneficial and should be encouraged and accommodated if
  • at all possible.
  • A risk based approach works well in terms of identifying and ranking the risks as well as tracking the treatment and transfer of safety related risks.
Acknowledgement

Thanks to the NZTA and The Well-Connected Alliance for allowing this case study to be used. Also thanks to Peter Norfolk of Tonkin & Taylor, who was the Civil Design Manager for the Waterview Project.

8.2 Queenstown weather mast – weather reporting system

Set the scene

The introduction of night time flights into Queenstown airport showed the need for accurate reporting of the local weather. The weather reporting system filled the need by using weather stations located around the Queenstown basin.

These stations measure the wind speed and direction, temperature and humidity, and report to a main computer server through the cellular phone system.

The information is then made available to pilots, air traffic controllers and flight planners via the Internet. The information can also be sent to pilots whilst in flight.

The system was being upgraded to improve its robustness and reliability. This included replacing the masts used to support the system instruments. The masts require bespoke foundations and mounting plates. An additional complexity is that some of the weather stations are sited in remote hilltop locations with limited and difficult access.

The mast foundation is a concrete-filled hole in the ground with 4 threaded rods embedded. Each mast has a base plate fitted to the bottom. This base plate has holes which slide over the threaded rods, allowing the base plate to be secured with nuts and washers. The mast is assembled on site, with all instruments and cables attached whilst the mast is horizontal. The mast is then manually raised into the upright position, with the base plate sliding over the threaded rods as the mast reaches the vertical position.

What went wrong or what went right?

The original plan was to steady the base of the mast with a person's foot as the mast was raised. Whilst this traditional method would work, a quick risk assessment showed there was a high likelihood of the person's foot slipping off the base of the mast resulting in an uncontrolled movement of the mast and possible damage to the mast and instruments or worse, injury to people.

The base plate was therefore redesigned to consist of 2 hinged plates. This allows one plate to be affixed to the mast as before, and the other plate to be attached to the foundation threaded rods whilst the mast is still in the horizontal position. The mast can then be raised to the vertical position in a fully controlled manner with no chance of the mast base slipping. Once the mast is upright the hinged plates are securely bolted together. This design also ensures the mast base cannot slip when the mast is lowered for periodic instrument maintenance.

[image] technical drawing of base plate assembly.

Base plate assembly.

A simple, low cost design change has effectively eliminated a potential hazard.

An early risk assessment has presented an opportunity to change a design to increase the safety of the system throughout its life in a cost effective manner.

[image] side by side images of a standard plate versus a hinged plate.

Standard design versus hinged plate

Thanks to Navigatus Consulting for allowing this case study to be used.

8.3 Compac service trolley

Set the scene

A service trolley was positioned above a fruit sorter. The fruit sorter has fruit conveying carriers attached to chains running at high speed. This unintentionally gave access to multiple nip points and hazards in the machine, which were otherwise not accessible. There was also a danger of falling from height through the machine and onto the floor.

The purpose of the trolley position above the machine is:

  • For trained personnel to conduct cleaning/routine maintenance when the machine is shut down and locked out. This task needed the personnel to be able to lie on the trolley floor and reach the machinery components below.
  • To give unauthorised personnel a platform to observe operations while the machine is running. For this the trolley needed to prevent access to all the moving parts underneath.

What went wrong or what went right?

The existing trolley was modified to incorporate the flexibility required for cleaning and maintenance tasks, while addressing the safety concerns identified by the risk assessment. This meant that the trolley needed to be configurable to be used in two distinct modes of operation. This was achieved through the installation of adjustable infill panels and the application of strict administrative controls.

  • Cleaning/maintenance mode (panel infills folded down): This mode gives access to the parts below the trolley, but mostly requires the machinery to be switched off and locked out first.
  • Observation mode (trolley panel infills lifted and secured in place): Prevents access to moving parts on an operating machine.

What lessons can we take from this project and share with the industry?

While the new trolley configuration provided safer access for maintenance staff and observers during standard operation, we learned that we must remain vigilant regarding unintended uses of the trolley at all lifecycle stages, such as machine installation onsite. For example, in one instance, the trolley started being used as an anchor point to protect installers while working at height. This would have been dangerous as the trolley is ill-equipped to be an anchor point and might have led to an incident.

[image] two images of service trolleys over fruit sorting conveyers.

Old service trolley vs new service trolley

Thanks to Suhas Shanbhogue of Compac for allowing this case study to be used.

8.4 Auckland Council special housing area: stormwater upgrade

Set the scene

Installation of new stormwater infrastructure to increase capacity and make allowance for a special housing area and an additional catchment. The project will also allow for separation of the combined wastewater/stormwater network.

What went wrong or what went right?

The catchment being serviced was located on a ridge with the downstream network located at a much lower elevation (a drop of 22 m over a 90 m length). The initial design called for a 24 m deep manhole in order to comply with the Stormwater Code of Practice.

A Safety in Design workshop was held with attendance by the designers, the Auckland Council Operations Team and the Auckland Council Design Team. The workshop identified safety issues with operating and maintaining such a deep manhole. Safety issues were also raised around the construction of such a deep structure. The designers were asked to redesign the alignment to remove the deep manhole. The removal of the deep manhole eliminated the safety concerns regarding working at depth during construction and operation.

In order for the design to be accepted, Auckland Council, in collaboration with the designers, relaxed the design criteria, specified more durable products and agreed to the design of an energy dissipation chamber. These changes were required in order to incorporate the shallow manhole and associated steeply graded pipe and high velocity flows.

What lessons can we take from this project and share with the industry?

In order to design and build a safe asset both the client and designer need to be prepared to think outside the box and investigate alternative products, installation methodologies and solutions.

[image] Design drawings of old vs new Auckland stormwater drains.

Initial design vs new design

Acknowldgement

Thanks to Auckland Council for allowing this case study to be used. Also thanks to Stantec (formerly MWH), who were the Design Consultants for this project.

8.5 Noise control for shearing clippers

Set the scene

Shearing equipment can generate high levels of noise during the shearing of sheep, meaning that shearers can be exposed to high noise levels for long periods during the season. Extended periods of exposure to high levels of noise can lead to temporary or permanent hearing loss. This may be partial or full.

What went wrong or what went right?

Research completed at Canterbury University demonstrated that noise levels could be reduced by simple redesign of the shearing equipment, such as the prevention of the core hitting the downtube. This was a simple, inexpensive and reasonably practicable fix to reduce the noise emission to shearers and minimise a health and safety risk.

To view this report in full, see: Mahn, J. (2010). Noise of sheep shearing systems. Part 2. Noise Source Identification. Christchurch. Canterbury University: Acoustic Research Group. Report 120.

Thanks to John Wallaart (Principal Advisor Biological and Chemical, WorkSafe New Zealand) for providing this case study.

Appendices

PDF

Appendix A: Glossary (PDF 46 KB)

PDF

Appendix B: General risks to consider when designing structures, plant or substances (PDF 173 KB)

PDF

Appendix C: Health and Safety by Design checklist for structures (PDF 49 KB)

Tool And Die Design Safety Recommendations

Source: https://www.worksafe.govt.nz/topic-and-industry/health-and-safety-by-design/health-and-safety-by-design-gpg/

Posted by: cotemecer2002.blogspot.com

0 Response to "Tool And Die Design Safety Recommendations"

Post a Comment

Iklan Atas Artikel

Iklan Tengah Artikel 1

Iklan Tengah Artikel 2

Iklan Bawah Artikel